To facilitate the connection of the Celtic Interconnector to the National Grid, our Stations Team at
Niaron Limited working on behalf of the
ESB successfully completed an 800 cubic metre concrete pour in less than 12 hours to the 4 bay 400kV transformer bund base this week.
A massive well done to our Stations Team and the
ESB's Project Delivery Team achieving this major milestone for the overall Interconnector project, an important part of Ireland’s long-term energy strategy. We want to thank
Roadstone Ltd. and CGA Concrete Pumping for their excellent service on the day.